GPU Colocation for Neoclouds in India: How to Evaluate Power Density, Cooling and Infrastructure (2026)

How Should a Neocloud Evaluate GPU Colocation in India? Quick Answer

A neocloud or GPU-as-a-service provider should evaluate a GPU colocation facility on five things: the kW per rack it can deliver in the specific hall, the liquid cooling it has installed, floor loading, the network inside and outside the building, and how fast contiguous capacity can be delivered and expanded. AI racks draw 30–80 kW and the densest reach 120–150 kW (KPMG), so a hall built for 8–12 kW racks cannot simply be reused.

What a Neocloud Needs from a Facility

A neocloud is a cloud provider built around GPU compute rather than general-purpose services. Its revenue depends on GPUs being powered, cooled and reachable, so the facility is part of the product. Interest in India is rising: at least six global neocloud companies backed by Nvidia were reported in July 2026 to be in talks with Indian data center operators to lease capacity for AI inference (CXO Digital Pulse).

RequirementWhat to look forWhy it matters
Power density30–80 kW per rack as standard, 120 kW or more for the densest systemsAn NVIDIA GB200 NVL72 rack draws approximately 120 kW (NVIDIA)
Liquid coolingDirect-to-chip loops with coolant distribution units, rear-door heat exchangers for residual heatAir cooling alone cannot remove this much heat
Floor loadingSlab or raised floor rated for heavy liquid-cooled racksDense racks with manifolds weigh well over a tonne
Internal networkSpace, pathways and cooling for a high-speed GPU fabricTraining clusters need GPUs close together and tightly connected
External networkCarrier-neutral facility, multiple carriers, cloud on-rampsCustomers must reach the GPUs with low latency
Contiguous capacityMegawatts in one hall or adjacent halls, not scattered racksClusters cannot be split across a campus
Speed and expansionDelivery date for phase one, reserved capacity for later phasesGPUs that sit unpowered lose value every month
RedundancyN+1 or 2N stated separately for power and coolingA cooling fault at this density becomes an outage within minutes
Data residencyCapacity in India under Indian jurisdictionRegulated and public sector customers require it

How to Evaluate Power Density

Density claims are easy to make and hard to compare. Separate four numbers:

  • Design density: what the hall was engineered for.
  • Deliverable density: what can be energised and cooled in your racks today.
  • Average versus peak: an average of 40 kW per rack across a hall is different from a guaranteed 80 kW in any rack.
  • Usable versus gross power: ask whether the quoted MW is IT load or includes cooling overhead.

Then check the electrical path to the rack: three-phase distribution, busway capacity, the redundancy level, and whether power is metered or billed flat. Rack density drives every other design choice, so get the figure in writing for the hall you will actually occupy.

How to Evaluate Cooling

Most racks above about 30–40 kW need liquid cooling, usually direct-to-chip. Because direct-to-chip systems still release part of their heat into the room, real GPU halls are hybrid: liquid to the chip, with air or rear-door cooling for the remainder. Ask the operator:

  • Which liquid cooling method is installed today, and in which halls?
  • Are coolant distribution units in place, and what is their redundancy?
  • What facility water temperature and flow can be supplied to the racks?
  • Who owns and maintains the secondary loop, the operator or the tenant?
  • How much heat per rack can the room handle in air?
  • What is the measured PUE at partial load, not only at full design load?

Liquid-cooled capacity is still scarce in India, which is why delivery dates matter as much as specifications. ANAROCK estimates India’s pre-committed AI demand pipeline at about 850 MW. Our guide to data center cooling methods explains each approach.

GPU Colocation Checklist for a GPU-as-a-Service Startup

A startup has different constraints from a hyperscaler: less capital, shorter planning horizons and customers who may arrive before the full cluster does.

  • Start with a right-sized commitment. Lease a first block you can fill, with contractual rights to adjacent capacity.
  • Decide what you own. Colocation means you buy and run the GPUs. Bare-metal or infrastructure-as-a-service means the operator supplies them.
  • Check the commercials. Price per kW, power pass-through, escalation, minimum term and what happens if your GPUs arrive late.
  • Plan operations. Remote hands, spares storage, staging space and 24×7 access for your engineers.
  • Confirm compliance. In-country hosting helps customers meet sector rules. See DPDP Act compliance for AI data.
  • Verify the operator. Funding, delivery record and power engineering capability decide whether later phases arrive on time.

Which Indian Data Centers Offer High Density for AI Compute

Several operators are adding liquid-cooled, high-density halls, and capability differs by hall rather than by brand. Compare specific facilities using the criteria above. Our comparison of AI-ready, high-density colocation and GPU hosting in India lists providers.

Techno Digital’s Chennai data center is designed for 100 kW and above per rack with liquid-cooling readiness, and the company offers colocation, infrastructure-as-a-service and build-to-suit models for neoclouds. Talk to Techno Digital.

Related Guides

FAQs

How do I evaluate power density for a GPU hosting deployment?

Ask for the deliverable kW per rack in your specific hall, whether that is an average or a guaranteed figure, and whether the quoted megawatts are IT load. Get it in writing.

What cooling does a neocloud GPU deployment need?

Usually direct-to-chip liquid cooling with coolant distribution units, plus air or rear-door cooling for residual heat. Most racks above about 30–40 kW need liquid cooling.

What should a GPU-as-a-service startup look for in a colocation partner in India?

High-density power, installed liquid cooling, contiguous capacity with expansion rights, carrier-neutral connectivity, clear commercials and an operator able to deliver later phases on time.

How much power does an AI rack need?

AI racks typically draw 30–80 kW, and the densest systems about 120 kW or more, against 8–12 kW for traditional racks.

Why does contiguous capacity matter for GPU clusters?

GPUs in a training cluster must sit close together to stay connected at high speed, so capacity spread across separate halls is far less useful.

Sources