Hyperscale Data Center Capacity in India by City and the Power Roadmap to 2027

Which Indian Cities Have the Most Hyperscale Data Center Capacity? Quick Answer

India’s hyperscale data center capacity is concentrated in a few cities. Mumbai and Navi Mumbai lead with about 890 MW of operational capacity in January–June 2026, followed by Chennai (214 MW), Delhi NCR (183 MW), Bengaluru (162 MW), Hyderabad (151 MW), Pune (133 MW) and Kolkata (22 MW), according to Cushman & Wakefield. The largest pipelines are in Mumbai (1,726 MW) and Hyderabad (710 MW). Rating agencies expect national third-party capacity to roughly double to 2.3–2.5 GW by March 2028.

Data Center Capacity by City

CityStateOperational (MW, Jan–Jun 2026)Pipeline (MW)What drives it
Mumbai and Navi MumbaiMaharashtra8901,726Subsea cable landings, financial sector, most cloud regions
ChennaiTamil Nadu214368Second subsea hub, links to Southeast Asia
Delhi NCR (Noida, Greater Noida, Gurugram)Uttar Pradesh, Delhi, Haryana183387Government and enterprise demand in the north
BengaluruKarnataka162100Technology and enterprise users
HyderabadTelangana151710Cloud regions and hyperscale campuses
PuneMaharashtra133258Overflow from Mumbai, enterprise demand
KolkataWest Bengal2284Gateway to eastern and north-eastern India

Figures are from Cushman & Wakefield’s H1 2026 update, which counts 1,789 MW operational across these seven cities. Mumbai alone holds about half.

Two newer locations sit outside the top seven but matter for hyperscale. Visakhapatnam is the site of Google’s US$15 billion AI hub with AdaniConneX and Bharti Airtel, and Jamnagar hosts Reliance and Meta’s announced 168 MW AI data center. In Hyderabad, TCS HyperVault plans a campus of up to 1 GW, with OpenAI as its first customer starting at 100 MW.

Why Capacity Concentrates in a Few Cities

Around 90% of India’s capacity sits in Mumbai, Chennai, Bengaluru and Delhi NCR (KPMG). Three things explain it:

  • Subsea connectivity: the Mumbai coastline carries about 95% of India’s international bandwidth, and Chennai is the secondary hub (Carnegie Endowment).
  • Customers: banks, cloud regions and large enterprises are already there.
  • Power and policy: states with dedicated data center policies and grid access attract the next phase. See the state policy guide.

Hyperscale Data Center Capacity Roadmap Through 2027

Forecasts differ because firms count differently: installed versus operational capacity, third-party versus all capacity, and calendar versus financial years. Read them as a range.

SourceEstimatePeriod
Macquarie Equity Research1.4 GW operational and about 1.4 GW under construction; capacity to double by 2027Reported October 2025
ICRAThird-party capacity of 2,400–2,500 MW, up from 1,250 MW in FY25By FY28 (March 2028)
Crisil Ratings2.3–2.5 GWBy FY28 (March 2028)
CareEdge RatingsAbout 4 GWBy FY30
ANAROCK1.8+ GW in H1 2026, rising to 6.7+ GWBy 2030
KPMGAbout 1.9 GW in FY26, rising to 7–7.5 GWBy FY30

The near-term picture is consistent. What is already under construction roughly doubles India’s operational base by 2027–28. ICRA expects about ₹90,000 crore of investment over FY26–FY28 to deliver it.

Hyperscale data center capacity is also being self-built on top of leased space. Hyperscalers have committed more than US$50 billion to build about 1.4 GW by 2029 (JLL). Microsoft has announced US$17.5 billion of investment in India by 2030 and Amazon more than US$35 billion by 2030.

Power Availability: The Real Roadmap

Announced megawatts become real only when the grid delivers them. The Minister of State for Power told Parliament in July 2026 that AI data centers alone could add 26.3 GW to electricity demand by FY32. Yet between FY22 and FY26, India achieved only about 80% of its annual transmission targets, and about a quarter of transmission projects face delays of a year or more (Ember).

So the practical scalability roadmap for a hyperscale campus through 2027 looks like this:

  • Phased energisation: large campuses are energised in blocks, so ask how many MW arrive in each phase and when.
  • Dual supply: power from two independent substations or feeders is becoming the baseline. Gujarat’s 2026 policy commits dual supply through independent feeders, and Tamil Nadu’s 2021 policy offered dual-grid supply above 50 MW.
  • State capacity targets: Gujarat targets 7.5 GW, Telangana has announced 5 GW of hyperscale capacity by 2029, and Uttar Pradesh targets 2 GW of additional capacity.
  • Grid connection support: Uttar Pradesh’s 2026 policy reimburses one grid connection for the first eight data center parks.

For a buyer, the question is not how much capacity a city has announced but how much has a firm energisation date. That is what time-to-power measures.

Techno Digital grew out of the Techno Electric Group, which has more than four decades of power engineering experience, and operates in Chennai and Delhi NCR with a Kolkata facility planned. Talk to Techno Digital.

Related Guides

FAQs

Which Indian city has the largest data center capacity?

Mumbai and Navi Mumbai, with about 890 MW operational in January–June 2026, roughly half of the capacity in India’s top seven cities.

Which city has the largest hyperscale pipeline after Mumbai?

Hyderabad, with a 710 MW pipeline, followed by Delhi NCR (387 MW) and Chennai (368 MW).

How much data center capacity will India have by 2027?

Macquarie expects capacity to double by 2027 from 1.4 GW. ICRA and Crisil both project about 2.3–2.5 GW by March 2028.

Why do capacity numbers for India differ between reports?

Firms measure different things: installed or operational capacity, third-party or all capacity, top seven cities or all markets, and calendar or financial years.

Is power available for hyperscale expansion in India?

Capacity is being added, but transmission is the constraint. Check the contracted load, phase-wise energisation dates and dual-substation supply for any specific site.

Sources