Data center Policies in India: State-by-State Guide 2026

Executive Summary

As of October 2026, three Indian states have issued new data center policies this year: Gujarat (Viksit Gujarat Data Center Policy 2026-2029), Uttar Pradesh (Data center Policy 2026) and Karnataka (Sustainable Data center Policy 2026-31, cabinet-approved). Most other states rely on dedicated data center policies issued between 2016 and 2025, or on broader IT policies that include data centers.

  • Common incentives: capital or interest subsidy, power tariff subsidy, electricity duty exemption, stamp duty waiver, open-access renewable power and essential-service status.
  • The new focus: 2026 policies tie incentives to green power (51% in Gujarat) and to scale (a 150 MW minimum in Gujarat, capacity targets of 7.5 GW in Gujarat and 2 GW in Uttar Pradesh).
  • Lapsed or closing windows: West Bengal’s 2021 policy expired in September 2026, and Tamil Nadu’s 2021 policy covers only units incorporated by 31 March 2026.
  • National layer: the Union Budget 2026-27 proposed a tax holiday to 2047 for foreign cloud companies serving global customers from Indian data centers.

India’s data center market at a glance

India’s installed data center capacity reached about 1.9 GW in FY26, up 2.4 times in three years, and is projected to reach 7-7.5 GW by FY30 (KPMG, July 2026).

IndicatorFigurePeriodSource
Share of world’s data generated in IndiaAbout one-fifth2026KPMG
Share of global data center capacity in India2-3%2026KPMG
Installed capacity~778 MW → ~1.9 GWFY23 → FY26KPMG
Projected capacity7-7.5 GWFY30KPMG
Announced investment commitmentsOver US$120 billionAs of March 2026KPMG
Share of capacity in Mumbai, Chennai, Bengaluru and Delhi NCR~90%2026KPMG
Operational capacity, top seven cities1,789 MWJanuary-June 2026Cushman & Wakefield
Capacity absorbed (leased)101 MW, 82% pre-committed hyperscaleJanuary-June 2026JLL
Extra power demand from AI data centers26.3 GWBy FY32Minister of State for Power, written reply to Parliament, July 2026 (report)

Estimates differ by source because firms count capacity differently (installed vs operational, all markets vs top seven cities).

National framework

India has no notified national data center policy; incentives come mainly from states, with three central measures setting the direction.

MeasureWhat it doesStatus
Union Budget 2026-27Proposed a tax holiday through 2047 for foreign companies providing cloud services to global customers using data center services in India, with Indian customers served through an Indian reseller entity; proposed a 15% safe-harbor margin on cost for related-party data center servicesProposed, February 2026
IndiaAI MissionNational programme to build AI compute capacity and the wider AI ecosystemIn force since 2024
Draft Data center Policy 2020 (MeitY)Proposed infrastructure status and a national framework for data centersDraft; not notified

In practice, investors compare state packages: power tariffs, electricity duty, land, approvals and renewable energy access are all set at state level.

State data center policies compared (October 2026)

This guide covers 17 states with a policy that includes data centers; the table lists their 18 policies (two for Karnataka), newest first. Details are taken from the official policy documents.

StatePolicyStatus, October 2026Headline targetKey incentivesOfficial document
GujaratViksit Gujarat Data Center Policy (2026-2029)In force; notified August 2026, three-year operative period7.5 GW capacity₹1/unit power subsidy and 100% electricity duty reimbursement for 20 years; up to 4% interest subsidy; 100% stamp duty; SGST reimbursement; 51% green power required; 150 MW minimumPDF
Uttar PradeshUttar Pradesh Data center Policy 2026In force; five years from July 20262 GW+ capacity, ₹2 lakh crore investment60% interest subsidy (parks); 7% capital subsidy (units); 25-50% land subsidy; 100% stamp duty; 50-75% wheeling and transmission concession for 25 years; PUE and renewable boostersPolicy · Notification · Guidelines (Hindi)
KarnatakaSustainable Data center Policy 2026-31Cabinet-approved September 2026; notification awaited1 GW IT load by 2031One-time ₹20 crore for PUE 1.00-1.20; water charge reimbursement for WUE 0.7-1.3 L/kWh; treated-water support; power and water site mappingNot yet published
KarnatakaKarnataka Data center Policy 2022-2027In force to 2027200 MW by 2025; ₹10,000 crore7% capital subsidy up to ₹10 crore; 10% land subsidy outside Bengaluru; industrial tariff with 30% green power; green tariff reimbursement; essential servicesOfficial PDF on file
RajasthanRajasthan Data center Policy 2025In force to 31 March 2029300 MW installed capacityCapital subsidy 10-20% of EFCI by project size, or tax-linked alternatives; 25% sunrise booster; 100% banking, wheeling and transmission waiver for captive renewables; 100% electricity duty exemption for 7 years; 75% stamp duty exemptionPDF
Andhra PradeshAndhra Pradesh Data Center Policy (4.0) 2024-29, G.O.Ms.No.6In force to 2029Up to 1 GW (state has since announced agreements for 6.5 GW)100% net SGST on capital goods or 10% capital subsidy; 100% stamp duty on first sale; industrial tariff; tailor-made incentives above 50 MW or ₹5,000 croreOfficial PDF on file
ChhattisgarhIndustrial Development Policy 2024-30 (special package for ITeS and data centers)In force to 2030—Net SGST reimbursement for 12 years up to 150% of FCI, or 35% FCI subsidy (caps ₹60-300 crore); 100% electricity duty exemption for 12 years; 100% stamp dutyOfficial PDF on file
BiharBihar IT Policy 2024In force; five years—30% capital subsidy up to ₹30 crore, or interest subvention up to ₹40 crore; 50% lease rental support for 5 yearsOfficial PDF on file
Madhya PradeshIT, ITeS & ESDM Investment Promotion Policy 2023In force—25% capex assistance up to ₹125 crore for first five anchor data centers (₹500 crore+); 15% up to ₹50 crore for others and edge data centers; ₹2/unit power tariff reimbursement for 5 years; electricity duty and wheeling reimbursementPDF
JharkhandIT, Data Center and BPO Investment Promotion Policy 2023In force; five years—Parks (25 MW+): 50% interest subsidy up to ₹50 crore, 25% land subsidy, dual-grid support; units: 25% capital subsidy up to ₹10 crore, electricity duty and power tariff reimbursementOfficial PDF on file
MaharashtraIT & ITeS Policy 2023, plus Green Integrated Data center Parks GR (October 2024)In force; dedicated data center policy in preparation₹95,000 crore IT and ITeS investmentEssential services status under ESMA; data center parks on MIDC land; electricity duty exemption; stamp duty exemption; free MIDC land and stamp duty waiver for first three green parksIT Policy 2023 · GR (Marathi)
HaryanaHaryana State Data Center Policy 2022In force; seven years₹7,500 crore100% electricity duty exemption for 20 years; 100% stamp duty reimbursement; 50-75% net SGST reimbursement for 10 years; parks 20 MW+ on 20 acresOfficial PDF on file
OdishaOdisha State Data center Policy 2022In force; five years from notification—20% capital subsidy up to ₹25 crore; 5% interest subsidy up to ₹25 crore; 30% power bill subsidy for 5 years; 100% transmission and wheeling reimbursement; 100% stamp duty on first transactionPDF
ManipurInformation Technology Policy for Manipur State 2022In force; five years—Special package for data centers within IT incentivesOfficial PDF on file
Tamil NaduTamil Nadu Data center Policy 2021, G.O.(Ms.) No. 33Covers units incorporated 1 April 2021 – 31 March 2026—Electricity tax waiver; concessional open access and cross-subsidy charges; dual grid for 50 MW+; stamp duty concession; land subsidy; ₹500 crore minimum investmentPolicy page · PDF
TripuraTripura Data center Policy 2021In force to 31 March 2027—Concessional power tariff; open-access exemption; bandwidth subsidy; rental and capital investment subsidyOfficial PDF on file
West BengalWest Bengal Data center Policy 2021Expired September 2026; new policy in preparation400 MW by 2025Essential services; 100% stamp duty exemption; electricity duty waiver for 5 yearsNotification
TelanganaTelangana Data centers Policy 2016No newer dedicated policy; 5 GW hyperscale target announced September 20265 GW by 2029 (announced)Dual power grid; renewable open access up to one-third of load; land in a dedicated data centers campusOfficial PDF on file

Incentives are summarized; eligibility thresholds, caps and conditions apply. Check the official document before relying on any figure.

State-by-state guide

Each entry gives the policy in force, what sets it apart and the state’s main data center markets.

Gujarat data center policy

The Viksit Gujarat Data Center Policy (2026-2029), launched in July 2026 and notified in August, is built for hyperscale. Projects need at least 150 MW of IT load, and 51% of power must be green. Incentives run for 20 years: a ₹1/unit power tariff subsidy and full electricity duty reimbursement. Capital subsidy (2.5% of EFCI) applies only in the Dholera region. Data centers get essential-service status under the Gujarat Essential Services Maintenance Act, 1972. The state has announced a ₹6 lakh crore investment goal; Jamnagar hosts Reliance and Meta’s 168 MW AI data center.

Uttar Pradesh data center policy

The Uttar Pradesh Data center Policy 2026 targets 2 GW of additional capacity and over ₹2 lakh crore of investment over five years. It follows the 2021 policy, under which approved projects reached ₹21,343 crore. The 2026 policy steers growth east with a 50% land subsidy in Bundelkhand and Purvanchal (25% elsewhere). It also rewards efficiency and AI: a PUE of 1.35 or lower, renewable energy above 70% and installing 700 or more FP64-grade compute units each raise the interest-subsidy ceiling.

Karnataka data center policy

Karnataka has two policies. The Karnataka Data center Policy 2022-2027 remains in force, with a 7% capital subsidy and land subsidy outside Bengaluru. The Sustainable Data center Policy 2026-31, approved by the cabinet in September 2026, targets 1 GW of IT load by 2031 and ties incentives to both power (PUE) and water (WUE) efficiency (The News Minute). It plans data center parks at Hoskote, Mangaluru and Mysuru. Bengaluru has about 162 MW operational.

Maharashtra data center policy

Maharashtra has no stand-alone data center policy yet; one is being prepared. Data centers are covered by the IT & ITeS Policy 2023, which grants essential-service status under ESMA and earmarks MIDC land for data center parks. An October 2024 Government Resolution offers free MIDC land and stamp duty waivers to the first three integrated green data center parks. Mumbai and Navi Mumbai hold about 890 MW, the country’s largest cluster.

Tamil Nadu data center policy

The Tamil Nadu Data center Policy 2021 applied to data centers incorporated between 1 April 2021 and 31 March 2026, with a ₹500 crore minimum investment. It offered electricity tax waivers, concessional open-access charges and dual-grid supply for loads above 50 MW. The policy notes that Tamil Nadu has India’s second-highest number of subsea cable landing stations. Chennai has 214 MW operational and delivered about half of India’s new supply in January-June 2026 (JLL).

Andhra Pradesh data center policy

The Andhra Pradesh Data Center Policy (4.0) 2024-29 (G.O.Ms.No.6, 14 November 2024) targets up to 1 GW and offers tailor-made incentives for projects above 50 MW or ₹5,000 crore. The state has since announced agreements for 6.5 GW (Deccan Chronicle) and, in September 2026, a 70% renewable-power requirement for data centers (Outlook Business). Google’s US$15 billion AI hub in Visakhapatnam anchors the pipeline.

Telangana data center policy

Telangana’s dedicated policy dates from 2016 and promised dual power grids, renewable open access and a data centers campus. In September 2026 the state announced a target of 5 GW of hyperscale capacity by 2029, as Microsoft opened its India South Central cloud region in Hyderabad (Indian Infrastructure). Hyderabad has 151 MW operational and a 710 MW pipeline, including TCS HyperVault’s 1 GW campus.

Rajasthan data center policy

The Rajasthan Data center Policy 2025, valid to 31 March 2029, is built around renewable energy. It waives banking, wheeling and transmission charges in full for captive renewable plants and allows unrestricted banking. Capital subsidy rises with project size, from 10% of EFCI for large projects to 20% for ultra-mega ones.

Haryana data center policy

The Haryana State Data Center Policy 2022 runs for seven years and targets ₹7,500 crore of investment. Its standout incentive is a 20-year electricity duty exemption. About two-thirds of Haryana lies in the National Capital Region, including Gurugram.

Madhya Pradesh data center policy

Madhya Pradesh covers data centers in its IT, ITeS & ESDM Investment Promotion Policy 2023. The first five anchor data centers investing ₹500 crore or more get 25% capex support up to ₹125 crore. It also has a dedicated edge track: 50 kW-1 MW sites qualify when at least 50 are proposed together.

Odisha data center policy

The Odisha State Data center Policy 2022 offers a 20% capital subsidy up to ₹25 crore, a 30% power bill subsidy for five years and full reimbursement of transmission and wheeling charges. Bhubaneswar is the main market.

West Bengal data center policy

The West Bengal Data center Policy 2021 was notified on 6 September 2021 for five years and expired in September 2026. The state government is preparing a new policy and considering industrial-park land for data centers (Business Standard). Kolkata, the digital gateway to eastern and north-eastern India, has 22 MW operational and an 84 MW pipeline.

Other states

  • Jharkhand: a combined IT, Data Center and BPO Investment Promotion Policy 2023 with separate incentives for data center parks (25 MW+) and units.
  • Chhattisgarh: a special package for ITeS and data centers in the Industrial Development Policy 2024-30, including 12 years of electricity duty exemption.
  • Bihar: the Bihar IT Policy 2024 lists data centers as a focus sector, with 30% capital subsidy up to ₹30 crore.
  • Tripura: the Tripura Data center Policy 2021, in force to 31 March 2027, offers a concessional power tariff and bandwidth subsidy.
  • Manipur: the IT Policy for Manipur State 2022 includes a special package for data centers.

Data center markets and operators by city

Mumbai holds about half of India’s operational capacity in the top seven cities, and Hyderabad has the second-largest pipeline. Operator lists below are indicative, based on public announcements, and not exhaustive.

City / clusterStateOperational (MW, Jan-Jun 2026)Pipeline (MW)Operators and anchor investors with facilities or announced campuses
Mumbai and Navi MumbaiMaharashtra8901,726NTT DATA, STT GDC, Equinix, Digital Edge, Yotta, CtrlS, Sify, Nxtra by Airtel, AdaniConneX, Princeton Digital Group, CapitaLand, Iron Mountain-Web Werks, Colt DCS
ChennaiTamil Nadu214368NTT DATA, STT GDC, AdaniConneX, Sify, Nxtra by Airtel, CapitaLand, Digital Connexion, Princeton Digital Group, Techno Digital
Delhi NCR (Noida, Greater Noida, Gurugram)Uttar Pradesh, Delhi, Haryana183387Yotta, AdaniConneX, CtrlS, NTT DATA, STT GDC, Nxtra by Airtel, Sify, Techno Digital
BengaluruKarnataka162100NTT DATA, STT GDC, Sify, Nxtra by Airtel, Iron Mountain-Web Werks
HyderabadTelangana151710CtrlS, Sify, STT GDC, NTT DATA, CapitaLand, AdaniConneX; AWS and Microsoft cloud regions; TCS HyperVault 1 GW campus (announced)
PuneMaharashtra133258STT GDC, Iron Mountain-Web Werks, Nxtra by Airtel
KolkataWest Bengal2284STT GDC, Sify, Nxtra by Airtel, Techno Digital
VisakhapatnamAndhra Pradesh—Gigawatt-scaleGoogle AI hub (US$15 billion) with AdaniConneX and Bharti Airtel
JamnagarGujarat—168 MW announcedReliance with Meta

Capacity figures: Cushman & Wakefield, H1 2026 (top seven cities). Visakhapatnam: Infrastructure Today. Jamnagar: HDFC Sky. Hyderabad cloud regions: Indian Infrastructure. Techno Digital sites: DCD.

Glossary of data center terms

TermDefinition
Time-to-powerThe time between site allocation and energization of a data center’s full contracted power load, with redundancy. Increasingly used to compare how ready a location is for large projects.
IT loadThe power drawn by servers, storage and network equipment, in megawatts (MW). Data center capacity in India is usually quoted as IT load.
PUE (Power Usage Effectiveness)Total facility power divided by IT load. A PUE of 1.0 is the theoretical ideal; Uttar Pradesh’s 2026 policy rewards a PUE of 1.35 or lower.
WUE (Water Usage Effectiveness)Liters of water used per kilowatt-hour of IT energy. Karnataka’s 2026-31 policy rewards a WUE of 0.7-1.3 L/kWh.
ColocationA data center where an operator leases space, power and cooling to several customers, who bring their own servers.
HyperscaleVery large campuses, usually 50-100 MW or more, built for or by cloud and AI companies such as Google, Microsoft and AWS.
Self-buildA data center a cloud company builds and runs for its own use rather than leasing from an operator.
Edge data centerA small facility close to users, cutting latency for real-time applications, streaming and AI inference.
Data center parkA designated campus with shared land, power, water and fiber infrastructure for several data center units.
Rack densityPower drawn per server rack, in kW. Traditional racks use 8-12 kW; AI racks typically 30-80 kW, and specialized ones up to 120-150 kW.
Open accessPermission for a large consumer to buy electricity, often renewable, directly from a generator rather than only from the local distribution company.
Wheeling chargesFees paid to move electricity across the transmission and distribution network from generator to consumer.
Energy bankingStoring surplus renewable generation as credits with the grid and drawing it back later.
Dual grid / dual feedPower supplied from two independent substations or feeders, so one failure does not cut supply.
Essential service statusA legal designation (for example under a state Essential Services Maintenance Act) that protects data center operations from strikes and shutdowns.
Tier III / Tier IVUptime Institute reliability ratings. Tier III allows maintenance without shutdown; Tier IV is fully fault-tolerant.
EFCI / FCIEligible Fixed Capital Investment / Fixed Capital Investment: the investment amount on which state subsidies are calculated, usually excluding land.
SGST reimbursementRefund of the state share of GST, used by several states as a capital incentive.

Frequently asked questions

Which Indian states have a data center policy in 2026?

Dedicated data center policies cover Gujarat (2026-2029), Uttar Pradesh (2026), Karnataka (2022-2027, with a 2026-31 policy approved), Rajasthan (2025), Andhra Pradesh (2024-29), Haryana (2022), Odisha (2022), Tamil Nadu (2021), Tripura (2021) and Telangana (2016). Jharkhand covers data centers in a combined IT, data center and BPO policy (2023). Maharashtra, Madhya Pradesh, Bihar, Chhattisgarh and Manipur include data centers in IT or industrial policies. West Bengal’s 2021 policy expired in September 2026, and a new one is being prepared.

Is there a national data center policy in India?

No. The Ministry of Electronics and IT published a draft Data center Policy in 2020, but it has not been notified. The main national measure is the Union Budget 2026-27 proposal of a tax holiday to 2047 for foreign cloud companies serving global customers from Indian data centers.

What incentives do state data center policies usually offer?

Most combine a capital or interest subsidy, a power tariff subsidy or industrial tariff, electricity duty exemption (5-20 years), stamp duty exemption, concessions on open-access, wheeling and transmission charges, dual-grid power and essential-service status. Newer policies add green-power conditions and rewards for low PUE.

How much power will India’s data centers need?

The Minister of State for Power told Parliament in July 2026 that AI data centers alone could add 26.3 GW to India’s electricity demand by FY32, nearly double the March 2026 estimate of 13.56 GW. That is why grid capacity and time-to-power now matter as much as subsidies.

What is time-to-power?

Time-to-power is the time between site allocation and energization of a data center’s full contracted load, with redundancy. For AI campuses that need hundreds of megawatts, delays in substations and transmission can cost more than an incentive saves.

Which cities have the most data center capacity in India?

Mumbai leads with about 890 MW operational in January-June 2026, followed by Chennai (214 MW), Delhi NCR (183 MW), Bengaluru (162 MW), Hyderabad (151 MW), Pune (133 MW) and Kolkata (22 MW), according to Cushman & Wakefield.

Further reading and sources

From Techno Digital: From Policy to Infrastructure: Why India’s Next Wave of Data Center Capital Will Follow Megawatts, Not MoUs by Ankit Saraiya, Director & CEO, Techno Digital — why time-to-power, grid readiness and integrated planning now decide where data center investment lands.

Related guides: How to Select a Hyperscale Data Center Campus in India · Hyperscale Data Center Capacity in India by City · What Is a Build-to-Suit Data Center?

Market data

Policy news

Official policy documents are linked in the comparison table above.